File #: 20-1026    Name:
Type: Written Report Status: Agenda Ready
File created: 6/24/2020 In control: City Council Legislative Meeting
On agenda: 9/22/2020 Final action:
Title: Consideration of Mitigation Measures for the Washington Metropolitan Area Transit Authority (WMATA) Planned Three-Month Platform Reconstruction Closure of Arlington Cemetery Station.
Attachments: 1. 20-1026_Attachment 1_Letter, 2. 20-1026_Attachment 2_AverageRidership, 3. 20-1026_Attachment 3_Rail Travel Time Impact from Spring 2021 Platform Improvement Project, 4. 20-1026_Attachment 4 - Presentation_ArlingtonCemeteryShutdown
City of Alexandria, Virginia
________________

MEMORANDUM



DATE: SEPTEMBER 16, 2020

TO: THE HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL

FROM: MARK B. JINKS, CITY MANAGER /s/

DOCKET TITLE:
TITLE
Consideration of Mitigation Measures for the Washington Metropolitan Area Transit Authority (WMATA) Planned Three-Month Platform Reconstruction Closure of Arlington Cemetery Station.
BODY
_____________________________________________________

ISSUE: Consideration of the mitigation measures for a three-month Blue Line closure between the Pentagon and Rosslyn Metrorail stations due to closure for platform reconstruction at Arlington Cemetery Station.

RECOMMENDATION: That City Council approve the attached letter (Attachment 1) to Washington Metropolitan Area Transit Authority (WMATA) regarding mitigation for the planned temporary closure of the Arlington Cemetery Station.

BACKGROUND: WMATA's Platform Improvement Project is a multi-year effort to improve the safety of platforms at 20 exterior stations with significant deterioration due to exposure to weather and the agents used during de-icing. This effort is being conducted in four phases. The first phase was the closure of six stations south of National Airport on the Blue and Yellow lines, impacting Alexandria during the summer of 2019. The second phase is being conducted during the summer of 2020 with the closure of four stations at the end of the Orange Line, which is not impacting normal travel in Alexandria. Phase 3, planned for mid-February 2021 to mid-May 2021, includes the Arlington Cemetery Station. This period was selected because it is a lower ridership period for the Phase 3 stations and it avoids the major events held at Arlington Cemetery. With the closure of Arlington Cemetery, trains cannot travel through the station, requiring that rail riders transfer at L'Enfant Station to travel to Blue Line stations in Arlington or District of Columbia.

DISCUSSION: To mitigate the impact of the Arl...

Click here for full text