Skip to main content
File #: 26-0446    Name:
Type: Written Report Status: Agenda Ready
File created: 11/13/2025 In control: City Council Legislative Meeting
On agenda: 12/9/2025 Final action:
Title: Consideration of Authorization for the City Manager to take the steps necessary on behalf of the City of Alexandria with respect to the Virginia Passenger Rail Authority (VPRA)'s Fourth Track Project.
Attachments: 1. 26-0446_Attachment 1 - Virginia Passenger Rail Authority Property Requests
City of Alexandria, Virginia
________________

MEMORANDUM



DATE: DECEMBER 4, 2025

TO: THE HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL

THROUGH: JAMES F. PARAJON, CITY MANAGER

FROM: EMILY A. BAKER, DEPUTY CITY MANAGER AND INTERIM DIRECTOR OF TRANSPORTATION AND ENVIRONMENTAL SERVICES

DOCKET TITLE:
TITLE
Consideration of Authorization for the City Manager to take the steps necessary on behalf of the City of Alexandria with respect to the Virginia Passenger Rail Authority (VPRA)'s Fourth Track Project.
BODY
__________________________________________________________________

ISSUE: City Council consideration regarding the authorization of the City Manager to take the steps necessary on behalf of the City with respect to VPRA's Fourth Track Project.

RECOMMENDATION: That City Council authorizes the City Manager to take such steps as are necessary on behalf of the City with respect to VPRA's Fourth Track Project.

BACKGROUND: The Virginia Passenger Rail Authority (VPRA) was created by the Virginia General Assembly in 2020 as a political subdivision of the Commonwealth. Pursuant to its enabling act, VPRA's purpose is to "increase passenger rail capacity, improve passenger rail services, ameliorate current and future traffic congestion on Virginia highways, and promote the industrial and economic development of the Commonwealth." To achieve these goals, VPRA is administering several rail corridor capital expansion projects, which requires land acquisitions and infrastructure construction. As part of the Transforming Rail in Virginia Initiative, VPRA is overseeing the Alexandria Fourth Track Project (Project) to design and construct almost six (6) miles of railroad track and related infrastructure in the City of Alexandria. The Project will install a fourth track parallel to the existing three-track segments, primarily using the existing rail corridor but also incorporating slivers of property necessary for the project. This Project will increase passenger capac...