Title: Consideration of the Acceptance of a State Grant Award for the Freedom House Interior Rehabilitation & Accessibility Improvements Project.
Attachments: 1. 27-1354_Attachment 1 - Award Letter
City of Alexandria, Virginia
________________

MEMORANDUM



DATE: OCTOBER 21, 2026

TO: THE HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL

THROUGH: JAMES F. PARAJON, CITY MANAGER

FROM: GRETCHEN BULOVA, DIRECTOR, OFFICE OF HISTORIC ALEXANDRIA

DOCKET TITLE:
TITLE
Consideration of the Acceptance of a State Grant Award for the Freedom House Interior Rehabilitation & Accessibility Improvements Project.
BODY
_________________________________________________________________

ISSUE: The Commonwealth of Virginia’s budget for the 2026/2027 fiscal year includes a $1,000,000 appropriation for the Freedom House Interior Rehabilitation & Accessibility Improvements Project.

RECOMMENDATION: That City Council:

(1) Accept the award issued on August 10, 2026 in the amount of $1,000,000, for the Freedom House Interior Rehabilitation & Accessibility Improvements Project.

(2) Authorize the City Manager to execute all the necessary documents that may be required.

BACKGROUND: The Commonwealth of Virginia’s budget for the 2026/2027 fiscal year includes a $1,000,000 appropriation for the Freedom House Interior Rehabilitation & Accessibility Improvements Project. This project was included in the 2026 legislative package.

The Freedom House Museum at 1315 Duke Street in Alexandria is a nationally significant historic site connected to the domestic slave trade. Previous work includes the exterior rehabilitation of the ca. 1812 Federal-style townhouse, completed in September 2025 by Oak Grove Restoration. This work stabilized the historic structure and restored the front façade to its appearance during the period of significance (1828–1861). Completed work included masonry repairs, paint analysis, rehabilitation of windows and woodwork, chimney stabilization, siding repairs, and water-intrusion mitigation.

Planning for the interior rehabilitation and accessibility phase is currently underway. The primary deliverable from this funding will be the construction documents and drawi...