Skip to main content
File #: 14-1866    Name: October 2013 Capital Allocations Report
Type: Written Report Status: Agenda Ready
File created: 9/11/2013 In control: City Council Legislative Meeting
On agenda: 10/22/2013 Final action:
Title: Consideration of Authorization of Recommended Capital Project Allocations and Planned Expenditures.
Attachments: 1. 14-1866_1_October 2013 Capital Allocations
City of Alexandria, Virginia
________________

MEMORANDUM



DATE: OCTOBER 16, 2013

TO: THE HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL

FROM: RASHAD M. YOUNG, CITY MANAGER /s/

DOCKET TITLE:
TITLE
Consideration of Authorization of Recommended Capital Project Allocations and Planned Expenditures.
BODY
_________________________________________________________________

ISSUE: City Council authorization of the recommended capital project allocations and planned expenditures.

RECOMMENDATION: That City Council authorize $9,389,026 for capital project allocations and planned expenditures for the capital projects as detailed in the Capital Improvement Program (CIP) Expenditure Summary (Attachment).

DISCUSSION: This docket item provides a summary of Capital Improvement Program planned expenditures (Attachment). It includes projects reflected in the City's Fiscal Year 2014 Capital Budget approved by City Council, or approved in capital budgets prior to FY 2014 with a CIP budget document page reference in the Attachment. A project title listing appears below and a detailed summary appears in the Attachment.

This will be the last capital allocations report formally presented to City Council for approval. Staff will begin the transition to quarterly capital project status reports, with the first quarterly status report anticipated to be presented to City Council at the January 28, 2014 Legislative meeting. The status report will provide an update on all active City capital projects, as well as a look forward to work anticipated to be completed in the next quarter (January 1, 2014 - March 31, 2014).

Allocations are recommended for the following projects:

Community Development ($694,000)
Fire Department Vehicles and Apparatus $694,000



Recreation & Parks ($123,000)
Tree and Shrub Capital Maintenance $123,000

Transportation & Transit - Public Transit ($8,382,025)
Alexandria Transit Company Bus Replacement and Expansio...

Click here for full text