File #: 26-0211    Name: Contract Management for Infrastructure, CMAR
Type: Ordinance Status: Agenda Ready
File created: 9/3/2025 In control: City Council Legislative Meeting
On agenda: 9/13/2025 Final action:
Title: Public Hearing, Second Reading, and Final Passage of an Ordinance to Amend and Reordain Section 3-3-70 (Design-Build and Construction Management Contracts) of Division 2 (Competitive Negotiation) of Article D (Contract Formation and Methods Of Source Selection) of Title 3 (Finance, Taxation and Procurement) of the Code of the City of Alexandria, Virginia, 1981, as amended. [ROLL-CALL VOTE]
Attachments: 1. 26-0211_Attachment 1: Ordinance Cover Section 3-3-70 - CAO Revised-Approved.pdf, 2. 26-0211_Attachment 2: Ordinance Amendment to Section 3-3-70 - CAO Revised-Approved.pdf
City of Alexandria, Virginia
________________

MEMORANDUM


DATE: SEPTEMBER 8, 2025

TO: THE HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL

THROUGH: JAMES F. PARAJON, CITY MANAGER

FROM: KEVIN C. GREENLIEF, DIRECTOR, DEPARTMENT OF FINANCE

DOCKET TITLE:
TITLE
Public Hearing, Second Reading, and Final Passage of an Ordinance to Amend and Reordain Section 3-3-70 (Design-Build and Construction Management Contracts) of Division 2 (Competitive Negotiation) of Article D (Contract Formation and Methods Of Source Selection) of Title 3 (Finance, Taxation and Procurement) of the Code of the City of Alexandria, Virginia, 1981, as amended. [ROLL-CALL VOTE]
BODY

______________________________________________________________________________

ISSUE: Consideration of an amendment to Alexandria City Code Sec 3-3-70 Design-Build and Construction Management Contracts to bring it in harmony with a prior amendment to the Virginia Public Procurement Act.

RECOMMENDATION: That the City Council:

1. Introduce and pass on first reading Tuesday, September 9, 2025, the ordinance (Attachment 2) updating City Code Sec 3-3-70 to align with Virginia State Code; and

2. Set the ordinance for public hearing and final passage on Saturday, September 13, 2025.

BACKGROUND: Alexandria City Code Sec 3-3-70 provides regulations on the use of Design-Build and Construction Management Contracts. Specifically, paragraph (d) (6) currently restricts the amount of work to be performed by the construction manager on a project to 10% as measured by the cost of the work, with 90% to be performed by subcontractors. This restriction in the City ordinance no longer conforms with State law in regards to infrastructure construction projects.

On March 27, 2023, the controlling statute, Va. Code ?2.2-4382 (E)(5), was amended to include an exception concerning the percentage of work restriction, stipulating that "The provisions of this subdivision shall not apply to construction management contracts involving inf...